What projects are included?

The selection panel met on Thursday 11 May 2017 to consider the community feedback and finalise the list of projects to be funded under this program.

The project to be delivered are:

  • Former Bombala Area = 23 projects
  • Former Cooma Area = 37 projects
  • Former Snowy River Area = 40 projects
  • TOTAL = 100 projects

SCFMPP Summary Graph

 Theme Number of projects
 Estimate allocation
 Roads and Bridges
13  $3,171,001.08
 Buildings upgrades or modifications
 17  $1,636,044.22
 Public Health (Including cemeteries)
 6  $440,072.50
 Recreational facilities
 39  $5,581,620.38
 Renewable Energy
 6  $358,028.30
 Streetscape Projects
 19  $2,813,233.53
 TOTAL
 100  $14,000,000.00

Table 1: Funding allocation for each Theme in the SCFMPP

The delivery of these projects will take place between June 2017 and June 2019. A majority of
project require significant planning to be undertaken before works can commence.

To download a copy of adopted projects click here