Scheduled Road Works

Council undertakes grading of unsealed roads in accordance with an adopted road hierarchy. This hierarchy is based on a practical approach which takes into account traffic counts, school bus routes, residences on the road, as well as the road's accident history.

Whilst grading is scheduled in advance, it is often necessary to alter the program due to the determination of specific roads or unforeseen circumstances. If the grading schedule is altered, a revised program will be placed on Councils website.

We attempt to maintain all roads in a serviceable condition within given budgetary and resource constraints. However there are times (e.g. during prolonged wet or dry weather) where the condition of unsealed roads may deteriorate and motorists will need to drive to the prevailing conditions.

Should road users identify a particular problem or are concerned about the significant deterioration of a road, please contact us and we will arrange for an inspection.

  1. Maintenance Grading
  2. Projects
  3. Planned Construction
  4. Quarries
  5. RMS Ordered Works
  6. Reactive Maintenance
  7. Resheeting
  8. Scheduled Maintenance
The grading schedule is subject to change dependent on asset and weather conditions. 
 Road Name 
 Proposed Month for Grading 
 Completion Date 
 Abington Park Road August 2017   Completed August 2017
 Avon Lake Road October 2017  Completed October 2017 
 Avonside Road July 2017  Completed July 2017 
 Badja Road
November 2017
  Completed December 2017
 Barry Way Road December 2017   Completed December 2017
 Beresford Road (Numeralla end) February 2018   Completed February 2018
 Big Flat Road July 2017  Completed July 2017 
 Big Flat Road February 2018   Completed February 2018
 Big Jack Road October 2017  Completed October 2017 
 Big Yard Road  August 2017  Completed August 2017
 Black Lake Road September 2017  Completed September 2017 
 Black Lake Road March 2018   
 Black Range Road
 November 2017
 Completed November 2017
 Bligh Street January 2018  Completed January 2018 
 Bobeyan Road August 2017  Completed August 2017 
 Bug Town Road August 2017  Completed August 2017 
 Bukalong Sliding Road October 2017  Completed October 2017 
 Bumbalong Road December 2017   
 Bundarra Road February 2018   Completed February 2018
 Burra Road  July 2017  Completed July 2017
 Caddigat Road 
 November 2017
 Completed November 2017
 Cambalong Road August 2017  Completed August 2017 
 Carlaminda Road
 November 2017
 Completed November 2017
 Chapman Street January 2018  Completed January 2018 
 Chong's Road
 November 2017
 Completed November 2017
 Collins  Road 
 November 2017
Completed  January 2018
 Coolumbooka Road September 2017  Completed September 2017 
 Cootralantra Road February 2018   
 Cottage Creek Road October 2017   Completed November 2017
 Craigie Range Road January 2018   Completed January 2018
 Delegate Road December 2017   
 Delegate River Road December 2017  Completed January 2018 
 Dragon Swamp Road
 November 2017
 Completed November 2017
 Dry Plains Road September 2017   Completed December 2017
 Falls Road October 2017  Completed October 2017 
 Frampton Road December 2017  Completed December 2017 
 Frying Pan Road October 2017   Completed November 2017
 Gillans Road August 2017  Completed August 2017 
 Gullies Road August 2017   Completed August 2017
 Gunningrah Road March 2018   
 Hickory Dale Road July 2017  Completed July 2017 
 Hilltop Road August 2017  Completed August 2017 
 Ironmungie Road September 2017  Completed September 2017 
 Jerangle Road February 2018  
 Kalkite Road August 2017  Completed August 2017 
 Kiah Lake Road March 2018   
 Kingston Road
 November 2017
 Completed November 2017
 Link Road March 2018   
 Lower Snowy Road December 2017  Completed December 2017 
 Micalago Road November 2017  Completed November 2017 
 Middle Flat Road February 2018  Completed February 2018 
 Mila Road February 2018   
 Mount Forest Road November 2017  Completed November 2017 
 Mountain View Road August 2017  Completed August 2017 
 Mt Delegate Road December 2017   Completed December 2017
 Mt Marshall Road October 2017  Completed October 2017 
 Nitholm Road February 2018  Completed February 2018 
 Old Kybeyan Road October 2017  Completed October 2017 
 Palarang Road August 2017  Completed August 2017 
 Poddy Hut Road September 2017  Completed September 2017 
 Poveys Road December 2017   
 Powers Road January 2018  Completed January 2018 
 Prestons Road July 2017  Completed July 2017 
 Quinburra Road February 2018  Completed February 2018 
 Richardson's Road March 2018   
 Sandy Flat Road March 2018   
 Seven Gates Road September 2017  Completed September 2017 
 Shannons Flat Road August 2017  Completed August 2017 
 Slap Up Road March 2018   
 Smiths Road July 2017  Completed July 2017 
 Smiths Road March 2018   
 Springfield Road September 2017  Completed September 2017 
 Stradbroke Road 
 November 2017
 Completed November 2017
 Stewartfield Road November 2017   Competed November 2017
 Stoney Creek Road March 2018   
 Tantawangalo Road
 November 2017
 Completed December 2017
 Tillabudgerry Road January 2018  Completed January 2018 
 Tinderry Road  July 2017  Completed July 2017
 Tip Tree Road August 2017  Completed August 2017 
 Tombong Road 
 November 2017
 Completed December 2017
 Tuross Road October 2017  Completed November 2017 
 Warrens Corner Road November 2017  Completed November 2017 
 West Lynne Road September 2017  Completed September 2017 
 Westons Road February 2018   
 WJ Drive Road
 November 2017
 Completed December 2017