Unsealed Road Grading Program 2024/25

A large yellow grader working on an unsealed (gravel) road

This schedule lists Council's scheduled unsealed road grading works for the 2024/25 financial year.

Snowy Monaro Regional Council's unsealed road network is approximately 1700km in total. Council’s service level for preventative maintenance for gravel roads was adopted at the extraordinary meeting held on Thursday 27 June 2024. The relevant excerpt of this Council resolution states:

b.    Set the service levels for preventative maintenance for gravel roads as follows: 
       i.     Annual maintenance grade for regional and collector roads
       ii.    Maintenance grade every two years for local roads
       
iii. Maintenance grade every three years or as required for minor access roads.

When reviewing the Program, the following should be noted:

  • The occurrence of grading has been assigned for this financial year only.  The timing/occurrence of works in subsequent years will vary.
  • Whilst maintenance is scheduled in advance, it is often necessary to alter the program due to the changing condition of specific roads or other unforeseen circumstances.
  • The scheduled works outlined in this program are set by the Council’s agreed level of service, at times Council may receive funding through Disaster Relief packages that enables Council to conduct works outside of the agreed level of service.  Disaster Relief packages can be executed by Council resources or by contractors.  Resources may be redirected to ensure Disaster Relief works are completed prior to funding deadlines.
  • During inclement weather the schedule may be temporarily suspended as continuing to carry out works on wet roads can cause further damage.
  • If a road of concern is not listed on the schedule please contact Council’s road department on 1300 345 345.

Type of work definitions:

Preventative Maintenance Grade: Full formation grade of road surface, this will occur in accordance with Council’s agreed level of service. Some roads may fall into two categories (eg: local and collector) therefore the hole length of road may not be graded at the same time.

Reactive Maintenance Grade: Partial grade of road surface. These works may be carried out in contrary to the agreed level of service, generally these works are remediating areas that are a risk to the community.

Resheeting:  Addition of new gravel to the gravel road surface. These works will be carried out on a section of the road as specified to prolong the life span of the unsealed road.

The full resolution can be found here.

Upcoming Schedule

This schedule lists Council's scheduled unsealed road preventative maintenance grading and resheeting works for May to June 2025.

Road Name Locality Type of Work
Bundarra Road Jerangle Preventative maintenance grade 
Jerangle Road  Jerangle Preventative maintenance grade
Carlaminda Road Carlaminda Preventative maintenance grade
Caddigat Road Adaminaby Preventative maintenance grade
Mila Road  Mila/Craigie Preventative maintenance grade 
Lansdowne Road Mila Preventative maintenance grade
Trevanions Road Mila Preventative maintenance grade
Link Road  Mila Preventative maintenance grade
Corrowong Road Corrowong Preventative maintenance grade
Barry Way  Moonbah Preventative maintenance grade
Golden Age Road  Moonbah Preventative maintenance grade
Old Grosses Road  Moonbah Preventative maintenance grade
Tinderry Road  Tinderry/Michelago  Preventative maintenance grade
Wollondibby Road Crackenback Preventative maintenance grade
Poveys Road  Colinton Preventative maintenance grade
Micalago Road  Michelago Preventative maintenance grade
Tinderry Road  Tinderry/ Michelago Resheeting for 2km from Jinjera Road to Egans Road
Abington Park Road  Moonbah Resheeting end of seal to Mountain View Road 
Springfield Road  Springfield Resheeting for 2.7km from Bobundarra Lane towards Avon Lake Road
Jerangle Road  Jerangle Resheeting end of seal to Kasey’s Road 
Big Yard Road  Moonbah Resheeting from cattle ramp at 1.29km mark to Rendezous Creek
Arable Road  Arable Resheeting for 1km from Bobundarra Road intersection towards Arable 
Caddigat Road  Adaminaby Resheeting for 1.5km from Kingston Road towards Dry Plains 
Kingston Road  Adaminaby Resheeting for 1.5km from Caddigat Road intersection towards Stradbroke Road 

 

Completed Works

These roads were completed as scheduled in the January to April 2025 period:

Road Name Locality Length (km)
Arable Road Arable 14.704
Framptom Road Coolringdon 3.365
 Powers Road Delegate 1.423
 Pump Road Delegate 0.48
Common Road Delegate  0.635
Blagownie Delegate 5.15
Bobeyan Road Bolaro 18.52
Ashvale Road Bolaro 2.3
Smiths Road The Angle 12.67
Kalkite Road Kalkite 1.798
Green Hills Road Peak View 1.97
Peakview Road  Numeralla 28.08
Pollys Gully Road  Peak View 0.24
Tumbledown Road  Peak View 1.655
Stoney Creek Road  Rocky Plain 7.9
Wright Hill  Shannons Flat 0.94
 Yaouk Road Adaminaby 32.76
Hickory Dale Road  Berridale 0.97
Access Road 1  Jerangle 2.83
Phillips Road Jerangle 0.46
Shepherds Flat Road Jerangle 4.39
Sandy Flat Road  Bibbenluke 8.08
Black Lake Road  Bibbenluke 9.396
Falls Road  Bombala 0.195
McKeachie Street  Bombala 0.22
Murphy Street  Bombala 0.23
Palarang Road  Bombala 16.43
Cambalong Road Cambalong 14.411
Avonside Road  Avonside 4.431
Geikle Creek Road  Avonside 3.07
Callemondah Road  Shannons Flat 4.94
Shannons Flat Road  Shannons Flat 12.561
Cathcart Streets  Cathcart