Bridge Renewal Program

Project Type: Upgrade

Project Location: Various

Funding: Various

What are we doing?

Thanks to generous support from the NSW Government, Council can undertake a bridge renewal program to upgrade some of our aging infrastructure and provide secure transport networks for years to come.

The current bridges planned for upgrade are:

  • Matong Bypass (Kelly’s) Bridge
  • Cambalong 1 Bridge – Cambalong Road (over Bombala River)
  • Ryrie Street Bridge - Michelago
  • Rossys Creek Bridge - Corrowong Road, Corrowong
  • Kellys Bridge - Matong Road, Jimenbuen
  • Cowbed Bridge - Rocky Plain Road, Berridale
  • Boolboolma Crossing – Tinderry Road, Anembo

Bridge Pic - Blue - April 24.PNG

Latest Update

Kelly's Bridge, Matong Road - COMPLETED

  • Upgrade design and piling by contractor, sealing by contractor, abutments repairs approach roads, and signage by Council staff.
  • Abutment reinforcement work completed.
  • Both bridge approach roads upgraded and sealed.
  • Bridge terminal guard rail repairs completed.
  • Project complete and the bridge open to traffic 1 May 2025.

 

Ryrie Street Bridge - COMPLETED

  • Bridge design and construction by contractor, sealing by contractor, box culvert, and Ryrie Street construction, including guide posting and signage by Council staff.
  • Ryrie Street extension to Micalago Road constructed and sealed.
  • New single lane bridge across Michelago Creek construction complete 24 July 2024.
  • Project complete and open to traffic 10 August 2024.

 

Rossy’s Creek Bridge - COMPLETED

  • Bridge design by contractor, sealing by contractor, bridge construction abutments/approach roads, and signage by Council staff.
  • New dual lane bridge across Rossys Creek construction complete 24 July 2024.
  • Approach roads constructed and sealed.
  • Project complete and open to traffic 15 October 2024.

  

Cambalong 1 - COMPLETED 

  • Bridge design and construction by contractor, sealing by contractor, abutments/approach roads, and signage by Council staff.
  • Construction is a 120m single lane concrete bridge commenced: Nov 2023
  • Bridge construction completed: Dec 2024
  • Guard rail terminals complete and approach roads sealed: Dec 2024
  • Bridge open to traffic: Jan 2025
  • Old bridge demolished and project practical completion:  Feb 2025

 

Cowbed Bridge

  • Bridge design and construction by contractor, sealing by contractor, bypass construction abutments/approach roads, and signage by Council staff.
  • Construction of a three span dual lane steel/concrete bridge commenced: March 2025
  • Bridge construction completed: May 2025
  • Guard rail terminals and approach road construction to commence late: May 2024
  • Bridge planned open to traffic: June/July 2025

 

Boolboolma Crossing

  • Bridge design and construction by contractor, sealing by contractor, bypass construction abutments/approach roads, and signage by Council staff.
  • Construction of a 35m single lane concrete bridge is programmed to commenced: June/July 2025
    • New road alignment design completed
    • Design and construction tender for a 35m single lane concrete bridge awarded
  • Construction of a temporary bypass commenced. 

 

Matong Bridge (Numbla Creek Bridge)

  • Bridge design and construction by contractor, sealing by contractor abutments/approach roads, and signage by Council staff.
  • Construction is a two span single lane steel/concrete bridge commenced: October 2024
  • Bridge construction completed: December 2024
  • Guard rail terminals and approach road sealing completed: May 2025
  • Bridge practical completion and open to traffic: March 2025

 

Cambalong Creek Bridge Gunningrach Road.

  • Construction by Council staff, piling by contractor, design by External Eng.
  • Construction is a 42.6M three span single lane steel bridge commenced: February 2025
  • To date:
    • Piles driven, concrete filled, and blinding slabs poured
    • Beaching rock placed, around abutments and piles
    • New aligned approach roads constructed to 60% to facilitate bridge construction
  • Inquik delivery of 3 X 13.7m span InQuick bridge formwork, planned for 13 May 2025
  • Placement of headstock and abutment formwork to commence on delivery

 

Murrumbucca Creek Bridge, Billilingra Road.

  • Construction by Council staff, piling by contractor, design by External Eng.
  • Construction is a 12.2m three span dual lane concrete bridge.
  • Construction commenced: Jan 2025
  • Construction complete, bypass removed, and open to traffic: May 2025
  • Approach road sealing and road signage to be completed: late May/June 2025

 

Relevant links

For up-to-date traffic information please visit https://www.livetraffic.com.

Project Approval Documentation