Updated information on urban roadworks

Published on 14 March 2024

Road workers

Snowy Monaro Regional Council is undertaking a major upgrade of roads across the region. This investment totals more than a million dollars and is the largest road investment program in many years.

This program of works is outlined below and we ask for the community’s patience and understanding as these critical roads works are completed.

With a large program of work currently underway in Cooma, we acknowledge the concerns of some in the business community about the impacts to parking and temporary road closures required for the works to be done safely and within budget.

Council can confirm that there will be no roadworks or closures in any CBD precinct in the region across the Easter break to ensure no impact on the tourist period for our region.

Regrettably, our engagement with the Cooma business community has not met expectations and for this we apologise. Council regrets the inconvenience this essential work has had and challenges with advice on specifics of the projects.

Details on the projects are outlined below including key dates. Please note that these are subject to change due to inclement weather, etc. However, the teams and our contractors are working hard to have the work completed safely as soon as practical.

Road program details for other towns and villages are also included below.

Please contact us on 1300 345 345 or council@smrc.nsw.gov.au with any questions or concerns about this work.

Cooma roadwork schedule

Road

Start date

Finish date

Baron Street

Underway

Monday 25 March 2024

Commissioner Street

Underway

Monday 25 March 2024

Vale Street

Underway

Monday 25 March 2024

Orana Avenue

Underway

Monday 25 March 2024

Massie Street

Underway

Wednesday 10 April 2024

Soho Street

Underway

Wednesday 10 April 2024

Boundary Street

Monday 18 March 2024

Monday 8 April 2024

Mittagang Road

Thursday 21 March 2024

Monday 8 April 2024

Soho Street

Monday 25 March 2024

Monday 8 April 2024

Massie Street

Monday 25 March 2024

Monday 8 April 2024

Adams Avenue

Monday 25 March 2024

Monday 8 April 2024

Church Road

Wednesday 27 March 2024

Monday 8 April 2024


Urban roadwork schedule March and April 2024

Locality

Road

Start date

Finish date

Adaminaby

Cosgrove Street

Thursday 14 March

Monday 25 March

Adaminaby

Chalker Street

Thursday 14 March

Monday 25 March

Berridale

Cherry Lane

Monday 18 March

Friday 5 April

Berridale

Highdale Street

Monday 18 March

Friday 5 April

Berridale

Katri Close

Monday 18 March

Friday 5 April

Berridale

Highdale Street (Carpark)

Monday 18 March

Friday 5 April

Bombala

Bright Street

Tuesday 12 March

Monday 25 March

Bombala

Caveat Street

Tuesday 12 March

Monday 25 March

Bombala

Wellington Street

Tuesday 12 March

Monday 25 March

Jindabyne

Gippsland Street

Tuesday 2 April

Monday 15 April

Jindabyne

Thredbo Terrace

Tuesday 2 April

Monday 15 April

Jindabyne

Banjo Paterson Crescent

Tuesday 2 April

Monday 15 April

Jindabyne

Bogong Street

Tuesday 2 April

Monday 15 April

Jindabyne

Clyde Street

Tuesday 2 April

Monday 15 April

Jindabyne

Park Road

Tuesday 2 April

Monday 15 April

Jindabyne

Ingebyra Street

Tuesday 2 April

Monday 15 April

Jindabyne

Munyang Street

Tuesday 2 April

Monday 15 April

Old Adaminaby

Clancy Street

Thursday 14 March

Monday 25 March

Old Adaminaby

Hill Street

Thursday 14 March

Monday 25 March

Old Adaminaby

Banjo Street

Thursday 14 March

Monday 25 March

Old Adaminaby

Rainbow Street

Thursday 14 March

Monday 25 March